References

The key personnel of our business, as well as our suppliers, have accumulated sound experience in leasing and module-based construction of portable premises: comprehensive solutions for temporary premises (schools, day care centres), field offices of major industrial projects, VIP premises, clean rooms, drying premises …

Partner and COO Jukka Lehtinen has accumulated sound experience in project management, logistics, equipment renting as well as module-based construction. Jukka’s latest position was with the global market leader in the premises leasing business. His long and extensive familiarity with the business creates good premises for applying different approaches and bringing new ideas to the industry.

Alfamodul_torpparinm_1_www

 Torpparinmäki School, City of Helsinki 1/2014
Ca. 240 m2

• Wooden modules, KVR-delivery
• Designing & assembly period total 14 weeks
• Rental period 5 years
• Energy certificate class C
• Electrical heating
• Ventilation, heat recovery, class D2

Alfamodul_jkyla_1_www Jyväskylä Lyceum, City of Jyväskylä 12/2013
1200 m2

• 500 pupils, 45 teachers
• Designing & assembly period total 14 weeks
• Rental period 4 years
• Energy certificate class C
• Ventilation, heat recovery, class S2 (instead of required D2)

alfamodul_www_sjoki_out2_210x158

EPSHP Hospital, Recovery room,
Seinäjoki 11.4.2013 –

27 modules, ca. 400 m2
– delivery, complete installation
– ventilation, heat recovery
– planning & assembly period total 10 weeks
including hospital standard HVAC installation


Rajakyla_fk-1u Rajakylä School, Oulu 10.7.2012 –
38 modules ca. 520 m2
66 pupils + 12 personnel 

– ventilation, heat recovery
– energy sertificate class B
– assembly period total 5 weeks
– including classroom equipment
– pitched roof (corrugated iron)
– outdoor water and sewerage works
P1020397

Pirilä Kindergarten, Kempele 1.4.2012 –
47 modules, ca. 600 m2, 80 + 12 personnel
– delivery, complete installation
– ventilation, heat recovery
– energy sertificate class B
– designing and assembly period total 6 weeks
– assembly time 4 weeks incl. furnishing and 
  assembly of equipment (by Municpality)

Alfa_valvomo_tre1
Control rooms for a big engineering works
in Tampere district, 1.3.2012- 
8 modules, ca. 120 m2
– delivery, complete installation
– ventilation, heat recovery
– assembly (2 floors) in 3 days
– furnishing and equipment of offices
– sanitary modules, drying cabinets